Wednesday, September 10, 2014

Testing Procedures

Assembling the ROV
Testing Type: Assessment
Testing Stage: Preliminary
State of Solution: In construction
Condition of Testing: On dry land
Tools and Equipment: Claw, ROV hull, electrical components
1. Meat with team
2. Ensure each members' parts' locations meet the design requirements
3. Ensure each members' parts meet the parts' designs specifications and
limitations

To Test PlayStation Controller

Testing Type: Exploratory

Testing Stage: Preliminary
State of Solution: Stationary
Condition of Testing Stage: On dry land
Tools and Equipment: Completed controller, ROV, wire
1. Toggle all buttons interfaced with ROV
2. Ensure each button activates correct part of ROV
3. Identify and address all noted issues

To Test Camera Connection

Testing Type: Assessment

Testing Stage: Preliminary
State of Solution: Stationary
Condition of Testing Stage: On dry land
Tools and Equipment: Camera, LED screen, Ethernet cable
1. Turn camera on
2. Ensure camera image live feeds to LED screen
3. Identify and address all noted issues


To Test Claw

Testing Type: Assessment
Testing Stage: Preliminary
State of Solution: Stationary
Condition of Testing Stage: On dry land
Tools and Equipment: ROV claw, controller, ROV
1. Toggle button that activates claw
2. Ensure the button activates claw according to the claw's specifications and limitations
3. Identify and address all noted issues

To Test Waterproofed Tether
Testing Type: Validation
Testing Stage: Secondary
State of Solution: Submerged underwater
Condition of Testing Stage: Underwater
Tools and Equipment: Ohm meter, waterproofed tether cable, water
1. Use ohm meter to find initial resistance of cable
2. Submerge cable in water
3. Take cable out of water
4. Use ohm meter again to test new resistance of wet cable
5. Ensure that the second test results did not decrease from first test results